CTEC Completed Delivery of YJ6 1E-DCS Equipments

[2017-07-25]

On July 25, CTEC dispatched the last batch of 1E DCS equipments for Yangjiang Unit 6, which was the second 1000MW newly-built nuclear power unit adopting FirmSys platform.

CTEC signed the supply contract of Yangjiang 5&6 DCS in September 2013. It’s responsible for providing the integrated DCS solution for the two units, including safety (1E), non-safety DCS and DAS. The 1E DCS for Unit 5 was delivered in November 2016 without delays as a first application case.

The factory test for 1E DCS for Unit 6 was completed in May with “0” Non Conformity Report (NCR ) , and the delivery permit was received, issued by the Northern Regional Office of Nuclear and Radiation Safety Inspection (NRO), Ministry of Environment Protection (MEP) in June. The equipments were successively delivered to the plant since early July. The 1E DCS for Unit 6 absorbs the feedback of Unit 5 DCS project implementation, thus it has shorter project duration.